HomeMy WebLinkAboutResolutions - 2022-18 - authorizing the Mayor sign supplement #3 with ARC Architects for additional design and estimating services for the East Wenatchee City Hall Campus Improvements Project, Public Works Building, Proj 2019-11. - 4/5/2022City of East Wenatchee Resolution 2022-18 with Exhibit A Retain Resolution until no longer needed for City-business, then transfer to Washington State Archives (GS50-05A-16 Rev. 1) Page 1 of 2
City of East Wenatchee, Washington
Resolution No. 2022-18
A Resolution of the City of East Wenatchee, Washington authorizing the
Mayor to execute contract supplement #3 between the City of East
Wenatchee and ARC Architects for additional design and estimating
services associated with the East Wenatchee City Hall Campus
Improvements Project.
1. Alternate format.
1.1. Para leer este documento en un formato alternativo (español,
Braille, leer en voz alta, etc.), comuníquese con el secretario de la
Ciudad en alternateformat@eastwenatcheewa.gov, al (509) 884-9515
o al 711 (TTY).
1.2. To read this document in an alternate format (Spanish, Braille, read aloud, etc.), please contact the City Clerk at alternateformat@eastwenatcheewa.gov, at (509) 884-9515, or at 711 (TTY).
2. Authority.
2.1. RCW 35A.11.020 and RCW 35A.12.190 authorize the City Council to organize and regulate its internal affairs and to define the powers, functions and duties of its officers and employees.
THE CITY COUNCIL OF THE CITY OF EAST WENATCHEE DO RESOLVE AS FOLLOWS:
3. Authorization. The City Council authorizes the Mayor to execute a contract supplement that conforms to the language set forth in Exhibit A.
4. Severability. If a court of competent jurisdiction declares any provision in this resolution to be contrary to law, such declaration shall not affect the validity of the other provisions of this Resolution.
ARC Architects Agreement Supplement No. 1
Page 1 of 1
Agreement Supplement No. 3
The City of East Wenatchee (“City”) desires to supplement the agreement entered into
with ARC Architects (“Consultant”) dated April 7, 2020, to provide Professional
Architectural Services for the Design of a New Public Works Facility and Conducting a
Police Department Space Needs Assessment.
As allowed by Section 15, the parties desire to modify said agreement as follows:
5. Compensation –
a. Total Compensation. The City shall pay up to $19,836 in addition to the
original contracted not to exceed amount of $558,444 for performing extra
work set forth in Exhibit A. Total contract not to exceed amount is
$578,280.
All other provisions in said agreement remain in full force and effect except as expressly
modified by this supplement.
CITY OF EAST WENATCHEE
ARC ARCHITECTS
Signature:
______________________________
Signature:
________________________________
Jerrilea Crawford, Mayor
Jeff Wandasiewicz, Principal, AIA
Date:_________________________ Date:___________________________
ATTEST:
_____________________________
By:
______________________________
03/08/2022
East Wenatchee Public Works Facility Amendment #3 - Page 1 of 3
03/08/2022
Attn: Garren Melton, East Wenatchee Public Works Manager
Submitted via e-mail to GMelton@eastwenatcheewa.gov
RE: East Wenatchee Public Works Facility - Amendment #3 Civil & Cost Estimate Additional Services
Dear Garren:
ARC Architects is pleased to submit our fee proposal for Amendment #3 - Civil & Cost Estimate Additional Services for
the East Wenatchee Public Works Facility project, which will amend our existing Consultant’s Agreement dated
04/07/2020.
The Design Team’s total proposed fees $19,836 including reimbursable expenses, and our services will be billed
on an hourly basis.
Fee Proposal Overview
This enclosed Exhibit A-C provides both team summarized and individual team member scopes of services and
fees for ARC and our individual consultant team members for this project, and also includes 2022 hourly billing
rate tables for all team members. The project design team is currently limited to ARC Architects (Architect), Pacifi c
(Civil Engineer), and PDA (Cost Estimator).
Project Understanding
Additional services completed by the design team during Design Development and Construction Document
phases of the project.
Item ONE: Civil - Revise Water Connection
Revise the water main extension design to omit the new connection on 9th Street NE and instead connect between
an existing dead-end 8” pipe currently serving the City Hall campus and the 2” main on N Colorado Avenue.
Redesigned project utilities to facilitate addition of the water main as requested by EWWD, with accompanying
impacts to paving extents and grading. See consultants fee proposal with Exhibit C
Item TWO: Cost Estimate - Additional 50% DD Estimates
Prepare an independent 50% DD level cost estimate of revised buildings B1 and B2 in March 2021, including one
additional DD phase estimate with post estimate adjustments. Additional estimate required following program
change from separate administrative & maintenance buildings to hybrid building. The additional estimate is
beyond the base DD estimates. To keep pace with the project schedule, we asked PDA, our cost estimator, to “use”
pre-planned fee from his CD phase to provide the estimate of the re-design. PDA did so - but is now requesting to
make up that loss of fee. See consultants fee proposal with Exhibit C.
Sincerely,
Jeff Wandasiewicz | Principal, AIA
ARC Architects
D: (206) 383-7341
Attachments:
Exhibit A – ARC Cover Letter
Exhibit B – ARC Standard Billing Rate Schedule 2022
Exhibit C – Fee Proposal
architecture resource collaborative
EXHIBIT AEXHIBIT-A
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 1 of 8
03/08/2022
East Wenatchee Public Works Facility Amendment #3 - Page 2 of 3
EXHIBIT B
ARC Architects
Hourly Billing Rates Schedule 2022
All rates are reviewed annually each January
CLASSIFICATION $/HOUR
Consulting Principal $190
Managing Principal/Project Manager $175
Architect PM $140
Architect Designer $120
Staff Designer $110
Recent Graduate w/ Experience $105
Intern $90
Administration $100
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 2 of 8
03/08/2022
East Wenatchee Public Works Facility Amendment #3 - Page 3 of 3
EXHIBIT C
Amendment #3 - Additional Civil & Cost Estimate
ARC Architects 3/8/2022
remarks
fee mark-up subtotal
Architect $630 ARC Architects (Item 1)
Civil $9,500 1.1 $10,450 Pacific Engineering (Item 1)
Cost Estiamte $7,880 1.1 $8,668 PDA (Item 2)
Reimbursable Expenses $80 1.1 $88 PDA fees (Item 2)
Fee Proposal $19,836
2022 ARC BILLING RATES
principal / project manager (PM) $175
Architect PM (PA) $140
Staff Designer (SD) $110
ARC Fees - Item 1 PM PA SD remarks
In-house management
team coordination / contracting 220
Hours Total 220
Hourly Rate $175 $140 $110
Subtotals $350 $280 $0
$630 ARC fee minus reimbursables
ARC Fees - Item 2 PM PA SD remarks
In-house management
team coordination / contracting
Hours Total 000
Hourly Rate $175 $350 $0
Subtotals $0 $0 $0
$0 ARC fee minus reimbursables
East Wenatchee Public Works
FEE SUMMARY
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 3 of 8
200 South Columbia Street, Suite 300 l Wenatchee, WA 98801 I P 509.662.1161 l F 509.663.8227 l www.pacificengineering.net
January 31, 2022
Daniel Podoll, Principal
ARC Architects
119 S Main Street, Suite 200
Seattle, WA 98104-2579
PROJECT: City of Wenatchee Public Works Facility Improvements
Pacific Project No. 20026CA
SUBJECT: Amendment to Civil Engineering Scope of Work and Fees
Dear Daniel,
Thank you for the opportunity to provide civil engineering services for the East Wenatchee
Public Works Facility project. As part of the original Scope of Work, Pacific Engineering &
Design (Pacific) designed a water main extension to provide adequate fire flow to the Public
Works campus at full build-out.
This extension was designed based on preliminary input from East Wenatchee Water District
(EWWD) and their on-call engineer (RH2), in conformance with established EWWD standards
and requirements. Due to the very small diameter (2”) of the water main on N Colorado Avenue,
it was determined that a larger connection (12”) and extension from 9th Street NE would be
required. Permit plans reflecting this design were submitted to ARC on 9/27/2021.
Three months after permit submittal (12/29/2021), Devon Petit of RH2 reached out to Pacific
requesting that we revise the water main extension design to omit the new connection on 9th
Street NE and instead connect between an existing dead-end 8” pipe currently serving the City
Hall campus and the 2” main on N Colorado Avenue. RH2/EWWD determined that due to high
pressure in the portion of the water system in question, a smaller 8” pipe would be sufficient to
provide required fire flow.
In the three-month timeframe between permit plan submittal and receiving EWWD’s direction,
Pacific had taken the design drawings to a 95% CD level with 100% CD plans due 1/6/2022.
With the need to accommodate several utility types within a narrow utility corridor (e.g., public
water main, private fire loop, domestic water service, sanitary sewer service, stormwater
conveyance and storage, underground power and underground telecom), nearly every utility
had to be redesigned to facilitate addition of the water main as requested by EWWD, with
accompanying impacts to paving extents and grading.
Pacific’s original proposal stipulates “if extra services outside the scope of work are requested,
we will determine the fees associated with the extra service and communicate this to you so that
you can decide whether to add that extra service to the budget.” Ideally, Pacific would have
adequate time to estimate the level of effort involved, propose a scope change and associated
fees, and then perform the work following an authorization to proceed. However, in this case
EWWD design requirements were received merely one week prior to the scheduled 100% CD
deliverable date. EWWD’s out of scope request was addressed concurrently with other final
coordination and plan edits associated with reaching the 100% CD deliverable.
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 4 of 8
Daniel Podoll
Amendment to Civil Engineering Scope and Fees
January 31, 2022
Project No. 20026CA
Page 2 of 2
Pacific endeavored to incorporate the out-of-scope changes as expeditiously as possible to
minimize project delays with the understanding that our original budget would be reconciled
after the fact. The hours directly attributable to the associated out of scope effort equate to
$9,500. Pacific respectfully requests an amendment to our original design budget in that
amount.
Thank you for the opportunity to work with you on this project. Please call us at 509-662-1161 if
you have any questions or need additional information.
Sincerely,
Matias A. Rudback, PE
Principal, Senior Civil Engineer
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 5 of 8
Construction and Development Consulting
Project Delivery Analysts, LLC Page 1 of 2
ADDITIONAL ESTIMATING SERVICES PROPOSAL
prepared for
ARC Architects
119 S Main Street, Suite 200, Seattle, WA 98104
Project:
East Wenatchee Public Works revised 50% DD Phase
October 26th, 2021
I. Scope of Work:
Prepare an independent 50% DD level cost estimate of revised buildings B1 and B2 in March
2021, including one additional DD phase estimate with post estimate adjustments. The
additional estimate is beyond the base DD estimates completed last year and prior to the
upcoming CD phase estimate. Discuss the estimate and reconcile any comments with ARC.
Provide one additional Value Engineering estimate post draft.
II. Fee Summary:
III. Estimating Services - Activity Detail:
1. 50% DD Phase Work Summary:
Duration for Item “1” Scope………. 2 Weeks
Consultant Fee……………………. $7,880 Total
Personnel Involvement
Item “1”: Major Activities B McBride
M. Partner
Bill Jones
Partner
· Attend estimate document hand off teleconference with ARC 0 2
· Independent construction cost estimating at the 50% DD phase 1 35
· Update MEPS and site estimates: included above 0 0
· Perform post draft changes – eliminate mezz. and reduce finishes 0 3
· Provide post 50% VE estimate of mat slab vs. strip footing 1 4
· Review Owner soft cost budget as requested by ARC 0 3
Total Allocated Hours 2 47
Hourly Rates $180 $160
Fee Extension $360 $7,520
Item Deliverable Description Hours Rate Line Total Percent
1. Cost Estimating at 50% DD Phase:
Bill Jones (Project Estimator - Partner)
Bruce McBride (Managing Partner)
47
2
$160
$180
$7,520
$360
91.4%
7.6%
Subtotals: 49 $7,880 99.0%
Reimbursables: 1 Pct. $80 1.0%
TOTALS: 49 $7,960 100%
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 6 of 8
Construction and Development Consulting
Project Delivery Analysts, LLC Page 2 of 2
IV. Inclusions, Exclusions and Qualifications:
1. The above work is complete and all hours shown are actual hours.
2. The 50% DD estimate file included a comparison to the budget spreadsheet for B1
with reconciliation comments to each category.
3. This Additional Services proposal has the same general terms and conditions as our
base proposal dated 3/6/20.
4. Time was included per the above matrix to update MEPS and site estimates and
incorporate.
5. Industrial equipment is assumed by the Owner; not included in the construction costs.
6. A post DD / pre-CD value engineering estimate to determine the viabilities of a mat
slab versus continuous wall footings is included, based upon actual hours spent.
This PROPOSAL for CONSULTANT SERVICES tendered by:
PROJECT DELIVERY ANALYSTS, LLC
A California Limited Liability Company:
Pacific Northwest Division
9001 Springwood Avenue NE
Bainbridge Island, WA 98110
By: _______________________________
William Jones PE, Partner
William P. Jones
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 7 of 8
PROJECT DELIVERY ANALYSTS, LLC
Pacific Northwest Division
Attn:
Re:
encl:
Opinion of Probable Cost Narrative
Regards,
primarily the responsibility of the General Contractor. The premium included for Phase II measures is
shown on the summary sheet. Then, per usual custom, the estimating contingency was reduced in
William Jones, Partner
90% CD Phase Opinion of Probable Costs Estimate
recognition of more information and thus less risk at the CD phase. Future escalation
increased due to a higher annual rate anticipated for 2022 than thought when preparing the last estimate.
An underlying assumption to the escalation factor is steel costs will taper by the bid date next spring.
Thank you for the opportunity to prepare this CD level Opinion of Probable Costs. Please call should you
have any questions.
While an overhead storage mezzanine was included in the previous scope, a future second floor platform
over the office wing is new scope since last time. The design prepared by ARC and PCS is very efficient.
There were two compensating changes to the indirect costs portion of the construction estimate. First, the
General Conditions estimate, which is primarily a function of time, increased due to one additional
month of duration. PDA included costs of COVID-19 Phase II construction safety protocols, which are
competitive, underscoring the importance of opening up the bidding to multiple sources. The same theme
of managing high commodity prices through open bidding applies to the rolling overhead door category.
The CD level estimate is prepared using the same overall split-outs of Building and Sitework. A
comparison-to-previous spreadsheet is included to track changes since the 50% DD estimate of "B1" in
late March, 2021. It is important to consider that the decision to forego a recommended 100% DD estimate
in June led to a long scope span to bridge since the most recent estimate. In addition, eight months of
high material escalation occurred since the last estimate was completed. This created larger cost swings
within divisions than normal.
A pre-engineered metal building system shown since early DD was used for the structural, siding, roofing and
Opinion of Probable Costs - 90% CD
Dear Dan and Lauren,
and insulation categories. The insulated core metal wall and roof panels specified are an upgrade to the
to the typical PEMB system. The recent increase in steel costs is factored into the industry pricing we
received from our PEMB suppliers. However, the pricing received from our PEMB suppliers is very
Attached please find our Opinion of Probable Costs for the East Wenatchee Public Works Building "B" at
the 90% CD level. Though additional building scope items were found since previous and unit costs have
risen for most materials, reductions in the site costs compensated for a portion of the direct cost
increases while indirect costs balance an increase in General Conditions with a decrease in contingency.
Seattle, WA 98104
Mr. Dan Podell / Ms. Lauren Powers
East Wenatchee Public Works
Maintenance Building, Project #2020002 .00
November 19th, 2021
ARC
119 Main St, Ste #200
William P. Jones
CITY OF EAST WENATCHEE RESOLUTION 2022-18, EXHIBIT-A, Page 8 of 8