RESOLUTION NO. 2021 -09 A Resolution of the City of East Wenatchee, Washington adopting a revised and extended comprehensive transportation program referenced as the 2022-2027 Six-Year Transportation Improvement Program as required by RCW 35.77.010, containing a severability clause, and an effective date.
1. Alternate format.
1.1. Para leer este documento en otro formato (español, Braille, leer en voz alta, etc.), póngase en contacto con el vendedor de la ciudad al alternateformat@eastwenatcheewa.gov, al (509) 884-9515 o al 711 (TTY).
1.2. To read this document in an alternate format (Spanish, Braille, read aloud, etc.), please contact the City Clerk at alternateformat@eastwenatcheewa.gov, at (509) 884-9515, or at 711 (TTY).
2. Recitals
2.1. In accordance with the requirements of Chapters 35.77 and 47.27, the City Council of the city of East Wenatchee (“City Council”) has previously adopted a comprehensive transportation program (“Program”), and periodically revised and extended the Program by resolution.
2.2. The City Council has reviewed the work accomplished under the Program, determined current and future City transportation needs including non-motorized transportation and based upon the findings of fact and conclusions has prepared a Six-Year Transportation Improvement Program for the next six calendar years.
2.3. A public hearing was held by the East Wenatchee Planning Commission on May 25, 2021 to consider the draft Six-Year Transportation Improvement Program for 2022-2027 and formulate a recommendation for Council action. The time and place of the public hearing was published in accordance with city and state requirements. The Planning Commission unanimously recommended approval of the 2022-2027 Six-Year Transportation Improvement Program (4-0).
2.4. The City Council finds that it is in the best interests of the City and its citizens to adopt the Six-Year Transportation Improvement Program and adopts the findings of fact and conclusions contained in Section 6 of this Resolution.
City of East Wenatchee Resolution 2021-09 & Exhibit A – Six Year TIP Page 2 of 4
3. Authority.
3.1. RCW 35A.11.020 and RCW 35A.12.190 authorizes the City Council to organize and regulate its internal affairs and to define the powers, functions and duties of its officers and employees.
3.2. RCW 35.77.010 requires the annual adoption of a revised and extended comprehensive transportation program for the next six calendar years.
4. Purpose. The purpose of this Resolution is to adopt the Six-Year Transportation Improvement Program, as revised and extended for the calendar years of 2022-2027. The purpose of the TIP is to provide and advance plan as a guide in carrying out a coordinated street construction and maintenance program listing project locations, types of improvements, and estimated costs.
THE CITY COUNCIL OF THE CITY OF EAST WENATCHEE DO RESOLVE AS FOLLOWS:
5. Adoption of Six-Year Transportation Improvement Program. The City Council hereby adopts the Six-Year Transportation Improvement Program for the calendar years of 2022-2027, a copy of which is attached as Exhibit A to this resolution and is incorporated by this reference.
6. Findings of Fact and Conclusions of Law. The Legislative approval of this Resolution and adoption of the Six-Year Transportation Improvement Program is supported by the recitals listed above and the following findings of fact and conclusions of law.
6.1. Findings of Fact
6.1.1. RCW 35.77.010 requires that each city annually prepare and adopt a comprehensive transportation improvement program (TIP) for six calendar years.
6.1.2. The City adopted a comprehensive plan in accordance with the Growth Management Act (GMA), RCW Chapter 36.70A, which is a generalized, coordinated land use policy statement of the City. The Greater East Wenatchee Area Comprehensive Plan (2020) includes policies relating to transportation and street improvements in Chapter 8 and Capital Facilities Plan (CFP) in Chapter 6. The CFP includes policies relating to transportation and street improvements.
6.1.3. The City of East Wenatchee Capital Facilities Plan 2019-2024 was adopted on May 7, 2019, regarding city facilities and services.
6.1.4. An Environmental Checklist was prepared on April 30, 2021. A threshold determination and environmental review pursuant to RCW
City of East Wenatchee Resolution 2021-09 & Exhibit A – Six Year TIP Page 3 of 4
43.21C the State Environmental Policy Act was completed and a Determination of Non-significance (DNS) was issued on April 30, 2021.
6.1.5. The 2022-2027 Six-Year Transportation Improvement Program (TIP) provides a list of projects by location, type of improvement and estimated costs and identifies secured or potential funding sources.
6.1.6. On May 12, 2021, a notice of public hearing was published in The Wenatchee World.
6.1.7. An open record public hearing was held by the East Wenatchee Planning Commission on May 25, 2021.
6.1.8. By this reference, the planning staff file of records, including the staff report, noticing documents and SEPA documents are entered into the record.
6.1.9. Any Conclusion of Law that is more correctly a Finding of Fact is hereby incorporated as such by this reference.
6.2. Conclusions
6.2.1. The responsible lead agency made a determination that no more than a moderate effect on the environment is a reasonable probability as a result of the proposed action. The proper exercise of the threshold determination process as required by WAC 197-11 is that an environmental impact statement is not required to be prepared for this project. The processing of the proposal complies with the procedural and substantive requirements of the State Environmental Policy Act, Chapter 43.21C RCW, and Chapter 18.06 EWMC.
6.2.2. The processing of the proposal complies with the procedural and substantive requirements of RCW 35.77.010.
6.2.3. Proper legal requirements of Title 19 EWMC were met, and the community was given the opportunity to comment on the proposal at a duly noticed public hearing.
6.2.4. The proposed TIP is consistent with and implements the goals and policies in the comprehensive plan.
6.2.5. The proposed TIP is consistent with and implements the policies in the Capital Facilities Plan.
6.2.6. The proposal will not be detrimental to the general public health, safety or welfare.
City of East Wenatchee Exhibit A
Project
Number Project Title
Project
Length
(Miles)
Project Description
Total
Estimated
Cost
Year 1
2022
Year 2
2023
Year 3
2024
Year 4
2025
Year 5
2026
Year 6
2027 Phase
Phase
Start
Year
Federal
Fund
Code
Federal
Funds
State
Fund
Code
State
Funds
Local
Funds
5th St NE Pedestrian Facilities-Phase II Curb, gutter and sidewalk or pedestrian 4,631,136 PE 2020 SRTS 442,602 78,106Kentucky Avenue to N. Grover Pl Pathway, RRFB's and Illumination RW 2021 SRTS 165,750 29,2503,915,428 CN 2022 SRTS 3,328,114 587,314
Repair east- and westbound approach 710,000 65,000 PE 2022 STBG 56,225 8,775
lanes at Grant Rd and Eastmont Ave RWintersection 645,000 CN 2023 STBG 557,925 87,075 Grant Road Preservation 1,543,000 129,000 PE 2022 NHPP 129,000
Georgia Avenue to Kentucky Avenue 1,414,000 CN 2023 NHPP 1,414,000
19th Street NW Reconstruction Phase 1 0.25 Center turn lane, curb, gutter and sidewalk, stormwater conveyance 2,694,000 PE
RW
2019 ECY 250,000
NW Cascade Ave to SR 28 and street illumination.2,444,000 CN 2024 TIB 2,077,400 366,600
5 15th Street NE Reconstruction SR 28 to N Baker Ave 0.25 Full reconstruction, curb, gutter, sidewalk, storm
sewer, and illumination 2,100,000 2,100,000 ALL 2025 TIB 1,785,000 315,000
6 TBD- N Colorado Ave (Colby Ct to 3rd St NE) 0.46 Residential Overlay Program 227,136 227,136 ALL 2022 227,136
7 TBD- Dayton Ave (6th St NE to 5th St NE) 0.15 Residential Overlay Program 59,488 59,488 ALL 2022 59,488
Intersection Improvement 0.00 Traffic Signal or Roundabout 860,000 90,000 PE 2022 TIB 76,500 13,5003rd St SE and Rock Island Road 770,000 CN 2023 TIB 654,500 115,500
Intersection Improvement 950,000 100,000 PE 2026 TIB 85,000 15,000
9th St NE and Baker Ave 850,000 CN 2027 TIB 722,500 127,500
N Kentucky Avenue Reconstruction 1.03 Full reconstruction project: center left turn lane, 7,000,000 7,000,000 ALL 2027 STBG 1,750,000 TIB 1,500,000 3,750,000
10th Street NE to Grant Rd stormwater conveyance and street illumination.
11 TBD - 6th St NE (Colorado Ave to Eastmont Ave) 0.22 Residential Overlay Program 140,608 140,608 ALL 2023 140,608
Hamilton Ave Reconstruction (Standerfer Ave to Dead-end) PE 2021 70,000
0.13 830,000 CN 2022 CDBG 300,000 530,000
13 TBD - Standerfer Ave (Valley Mall Parkway to Hamilton Ave) 0.04 Residential Overlay Program 30,934 30,934 ALL 2023 30,934
14 TBD - Harrison Ct (10th St NE to Jackson Ave) 0.15 Residential Overlay Program 129,359 129,359 ALL 2023 129,359
15 TBD - Parkroy Place SE/2nd St SE (S Iowa Ave to S Houston Ave) 0.37 Residential Overlay Program 245,670 245,670 ALL 2024 245,670
16 TBD - Green Pl (Grant Rd to Dead-end) 0.11 Residential Overlay Program 145,998 145,998 ALL 2025 145,998
17 TBD - S Georgia Ave (Grant Rd to Dead-end) 0.11 Residential Overlay Program 75,432 75,432 ALL 2025 75,432
18 TBD - S Gilmore Ave (Grant Rd to Dead-end) 0.10 Residential Overlay Program 70,566 70,566 ALL 2025 70,566
Intersection Improvement Traffic Signal 910,000 91,000 PE 2024 TIB 77,350 13,650S Kentucky Avenue and 4th Street SE 819,000 CN 2025 TIB 696,150 122,850
19th Street NE Reconstruction- Phase II Full reconstruction project. Center turn lane, curb, 1,669,680 250,452 PE 2026 TIB 212,884 37,568
SR 28 to Baker Ave stormwater conveyance and street illumination.1,419,228 CN 2027 TIB 1,206,344 212,884
Eastmont Ave Preservation (9th St NE to North City Limit)Full width mill and repave.1,246,000 110000 PE 2025 TIB 178,500 31,500Update sidewalks to ADA standard 1,136,000 CN 2026 TIB 880,600 155,400
5th St NE Pedestrian Facilities-Phase III Curb, gutter and sidewalk or pedestrian 1,600,000 193,000 PE 2023 TIB 173,700 19,30022Eastmont Avenue to N Grover Ave 0.28 pathway, illumination, and intersection RWimprovement at Eastmont Ave 1,407,000 CN 2024 TIB 1,266,300 140,700
0.24
1.20
4
3 0.78
Grant Road/Eastmont Ave Intersection Repair
1
2
From 2022 to 2027Six Year Transportation Improvement Program
Expenditures
Edge grind, pavement repair, overlay. Upgrade
ADA ramps
900,000
0.65
0.11
Full reconstruction, curb, gutter, sidewalk, storm
sewer
Traffic Signal or Roundabout
8
20
10
21
9
19
12
0.00
0.00Exhibit 1
City of East Wenatchee Exhibit A
Project
Number Project Title
Project
Length
(Miles)
Project Description
Total
Estimated
Cost
Year 1
2022
Year 2
2023
Year 3
2024
Year 4
2025
Year 5
2026
Year 6
2027 Phase
Phase
Start
Year
Federal
Fund
Code
Federal
Funds
State
Fund
Code
State
Funds
Local
Funds
From 2022 to 2027Six Year Transportation Improvement Program
Expenditures
5th St NE Pedestrian Facilities-Phase IV Curb, gutter and sidewalk or pedestrian 1,100,000 135,000 PE 2023 TIB 114,750 20,250N James to N Jonathan Ave pathway, Illumination, and storm sewer RW965,000 CN 2024 TIB 820,250 144,750
5th St NE Preservation (Eastmont Ave to Kentucky Ave) Edge grind, pavement repair, overlay 914,000 110,000 PE 2025 TIB 93,500 16,500814,000 CN 2026 TIB 691,900 122,100
19th Street NE Reconstruction- Phase III Full reconstruction project, center turn 3,736,000 560,400 PE 2025 TIB 396,900 163,500Baker Avenue to Eastmont Avenue lane, curb, gutter and sidewalk, storm- RWwater conveyance & street illumination.3,175,600 CN 2026 TIB 2,249,100 926,500
Eastmont Avenue / 19th St NE Traffic Signal or Roundabout 950,000 100,000 PE 2025 STBG 86,500 13,500Intersection Improvements 850,000 CN 2026 STBG 735,250 114,750
27 Non-Motorized - Citywide Varies Provide sidewalks, crosswalks, signal modifications
and bicycle facilities.300,000 100,000 100,000 100,000 ALL 2025 CDBG 300,000
Eastmont Ave / 11th St NE 0.00 Install new signal with optical detection 920,000 95,000 PE 2023 STBG 82,175 12,825Intersection Improvements or roundabout 825,000 CN 2024 STBG 713,625 111,375
29 Pavement preservation - Non TBD Projects Varies Asphalt overlay, chip seal, crack sealing and other
methods 1,773,000 150,000 175,000 362,000 362,000 362,000 362,000 ALL 2021 1,773,000
30 Valley Mall Parkway Enhancement - Stage 1
From 6th Street NE to 9th Street NE 0.24 Widen sidewalks, reconfigure on street parking.928,000 928,000 ALL 2026 STBG 802,720 125,280
31 Valley Mall Parkway Enhancement - Stage 2
From 9th Street NE to SR 28 0.39 Widen sidewalks, reconfigure on street parking.720,000 720,000 ALL 2027 STBG 622,800 97,200
Legend TOTALS 39,280,007 5,466,052 3,632,901 5,609,670 4,717,996 4,350,852 14,476,828 11,486,686 16,209,128 11,594,193Projects with Secured Funding Highlighted in Yellow
PE - Engineering
CN - Construction
RW - Right of Way
1.10
0.58
0.17
0.00
28
24
25
26
23
S:\Planning Department\6 Year TIP\2022-2027 TIP\Exh A 2022 - 2027 TIP_DRAFT 5.2.2021.xlsxExhibit 1