CHANGE ORDER
Contract Number
Contract Title
Federal Aid Number
2018-04
Gateway Park Project
N/A
Change Order Number
Change Description
Date
4
Additional Removal Items
5/8/19
Region
Project Engineer
Phone Number
Dan Ireland
509-886-3265
Prime Contractor / Design -Builder
KRCI LLC
❑ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications or the RFP
❑� Change proposed by Contractor / Design -Builder
Change Description
Originated as RFI #5: Time Capsule Excavation, RFI #6: Existing Junction Box Grade, RFI #7:
Pothole Tree Location, and RFP #5: Existing Sign Base Removal.
Intent of this change order was to combine separate unforeseen removal items into one change
order.
Contract Plan Sheets: No Change
Construction Requirements/Special Provisions: No Change
Change in Contract Costs: The cost for this Change Order is the cost of KCRI work for unforseen
removal items including concrete removal and haul, additional excavation, potholing in tree locations,
removing sign base, lowering existing J-box, and trimming concrete around existing light base.
Contractor provided Force Account tracking information for work.
Concrete removal/haul = $4,497.56
Time capsule additional excavation = $238.49
Tree potholing = $418.82
Sign base removal = $345.27
Lower existing j-box = $239.96
Light base trimming = $102.10
Total Cost = $5,842.21
Working Days: There is no change to the critical path with this change.
Original Contract Amount
Current Contract Amount
Est. Net Change This C.O.
Est. Revised Contract Amount
$ 516,008.00
$ 516,478.40
$ 5,842.21
$ 522,113.42
Prime Contractor / Design -Builder
Signature or Method of Concurrence:
Project Engineer's Signature for Execution:
Distribution: Copy of Change Order Page & Memorandum Page w/Backup - Project Engineer
Copy of ONLY Change Order Page - Prime Contrac r Design -Builder
Copy of Change Order Page &Memorandum Pa w/ Backup - Region C struction Office
Original of Change Order Page & Memorandum a /Checkli,Yaryd roval Documentat
Contracting Authority Signature for Execution:
DOT Form 421-005A EF
Revised 12/09
Date
Date
ate
Dghstrurtion Office
141
/
Change Order Page
Change Order - Minor Change
Contract Number
Contract Title
Change Order Number
2018-04
Gateway Park Project 74
Brief Description of Problem / Reason for Entitlement:
Concrete removal/haul: Unforeseen concrete was found in various locations on site and had to be removed and hauled off
site.
Time capsule additional excavation: During excavation for the time capsule, a 18" diameter concrete pipe was found 2-2.5'
below grade. Additional excavation was required to move the capsule over approximately 2'.
Tree potholing: Due to concrete found on site, tree locations along 9th Street were potholed to identify potential planting
issues. Concrete was found in 1 of 3 locations and its removal was tracked under FA information for "Concrete
removal/haul".
Sign base removal: Former Texaco sign base was found to be above finish grade and had to be cut down.
Lower existing J-box: Existing junction box was found to be 0.2' above finish grade and was lowered to eliminate tripping
hazard in sidewalk.
Light base trimming: The existing light base was surrounded in concrete and additional work had to be done to create clean
edges for concrete sidewalk to be poured around.
Justification of Cost:
KCRI work was tracked via force accounts, in the exception of the sign base removal, which was
an agreed upon lump sum price.
Concrete removal/haul = $4,497.56 (FA tracking)
Time capsule additional excavation = $238.49 (FA tracking)
Tree potholing = $418.82 (FA tracking)
Sign base removal = $345.27 (LS price)
Lower existing j-box = $239.96 (FA tracking)
Light base trimming = $102.10 (FA tracking)
Total = $5,842.21
Calculated By
Date
Checked By
Date
Caitlin Mehall
5/8/19
Inspector
Date
Work Started
Work Completed
Item No.
Item
Group
Date
Unit
Quantity
RAM/QPL
Ledger no.
Post
Ckd
Est. No.
Distribution: Copy of Change Order Page & Memorandum Page w/Backup - Project Engineer
Copy of ONLY Change Order Page - Prime Contractor / Design -Builder
Copy of Change Order Page & Memorandum Page w/o Backup - Region Construction Office