Change Order - Minor Change
Contract Number Contract Title Federal Aid Number
2018-04 East Wenatchee Gateway Park N/A
Change Order Number Change Description Date
5 Additional Stair Wall 5/13/19
Region Project Engineer Phone Number
N/A Dan Ireland
Prime Contractor / Design -Builder
KRCI
❑ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications or the RFP
0 Change proposed by Contractor / Design -Builder
Change Description
The lower set of stairs on the project did not have a side wall on both sides of the stairs. The
Contractor constructed a side wall on the stairs to simply their forming construction of the stairs.
The Contractor proposed to leave the additional side wall in place instead of removing it. The
Contractor proposed a price for the additional side wall to remain in place and the City accepted.
Plans: The side wall will be the same as shown on SP-02 detail "Handrail with Concrete Staircase".
Specifications: There are no changes to the Contract specifications.
Schedule: This sidewall did not effect the contractors critical path. No working days will be issued.
Cost: A lump sum amount was proposed by KRCI (see attached). The cost was agreed upon by
the Engineer. The cost will be paid as a new bid item titled "Additional Stair Wall" in lump sum.
Original Contract Amount Current Contract Amount Est. Net Change This C.O. Est. Revised Contract Amount
$ 516,008.00 $ 522,113.42 $ 348.79 $ 522,462.1
Prime Contractor / Design -Builder
Signature or Method of Concurrence:
Project Engineer's Signature
Contracting Authority Signature for Execution:
Date _ 5�i14- C
Date 05/14/2019
Date
DOT Form 421-005A EF ✓ Change Order Page