RESOLUTION NO. 2019 -11
A Resolution of the City of East Wenatchee, Washington adopting a Six-Year Transportation Improvement Program for 2020-2025, directing the City Clerk to file this Resolution with the Secretary of Transportation, containing a severability clause, and an effective date.
1.Alternate format.
1.1. Para leer este documento en otro formato (español, Braille, leer en voz alta,etc.), póngase en contacto con el vendedor de la ciudad al alternateformat@east-wenatchee.com, al (509) 884-9515 o al 711 (TTY).
1.2. To read this document in an alternate format (Spanish, Braille, read aloud, etc.), please contact the City Clerk at alternateformat@east-wenatchee.com, at (509) 884-9515, or at 711 (TTY).
2.Recitals
2.1. In accordance with the requirements of Chapters 35.77 and 47.27, the CityCouncil of the city of East Wenatchee (“City Council”) has previously adopted a comprehensive transportation program ("Program"), and periodically modified the Program by resolution.
2.2. A public hearing was held by the East Wenatchee Planning Commission on May 28, 2019 to consider the draft Six-Year Transportation Improvement Program for 2020-2025. The Planning Commission unanimously recommended approval of the Program.
2.3. The City Council has reviewed the work accomplished under the Program, determined current and future City transportation needs including non-motorized transportation and based upon the findings of fact and conclusions has prepared a Six-Year Transportation Improvement Program for the next six calendar years.
2.4. The City Council finds that it is in the best interests of the City and its citizens to adopt the Six-Year Transportation Improvement Program and adopts the findings of fact and conclusions contained in Section 2 of this Resolution.
3.Authority.
3.1. RCW 35A.11.020 and RCW 35A.12.190 authorizes the City Council toorganize and regulate its internal affairs and to define the powers, functions and duties of its officers and employees.
Exhibit 1
City of East Wenatchee Resolution 2019-11 – Six Year TIP Page 2 of 4
3.2. RCW 35.77.010 authorize the preparation and adoption of a comprehensive transportation program for the next six calendar years.
4.Purpose. The purpose of this Resolution is to adopt the Six-Year TransportationImprovement Program, as revised and extended for the calendar years of 2020-2025 listing project locations, types of improvements, and estimated costs.
THE CITY COUNCIL OF THE CITY OF EAST WENATCHEE DO RESOLVE AS FOLLOWS:
5.Adoption of Six-Year Transportation Improvement Program. The City Councilaffirms that the City, through the adoption of this Resolution, hereby establishesthe Six-Year Transportation Improvement Program for the calendar years of2020-2025, a copy of which is attached as Exhibit A to this resolution and isincorporated by this reference.
6.Findings of Fact and Conclusions of Law. The approval of this Resolution andadoption of the Six-Year Transportation Improvement Program is supported bythe recitals listed above and the following findings of fact and conclusions of law.
6.1. Findings of Fact
6.1.1. The City adopted a comprehensive plan in accordance with the Growth Management Act (GMA), RCW Chapter 36.70A, which is a generalized, coordinated land use policy statement of the City. The Greater East Wenatchee Area Comprehensive Plan (2018) includes policies relating to transportation and street improvements in Chapter 8 and Capital Facilities Plan (CFP) in Chapter 6. The CFP includes policies relating to transportation and street improvements.
6.1.2. The City of East Wenatchee Capital Facilities Plan 2019-2024 was adopted on May 7, 2019 regarding city facilities and services.
6.1.3. A Notice of Public Hearing before the East Wenatchee Planning Commission was published in the Wenatchee World on May 16, 2019.
6.1.4. An Environmental Checklist was prepared on May 8, 2019. A threshold determination and environmental review pursuant to RCW 43.21C the State Environmental Policy Act was completed and a Determination of Non-significance (DNS) was issued on May 9, 2019.
6.1.5. The 2020-2025 Six-Year Transportation Improvement Program (TIP) provides a list of projects by location, type of improvement and estimated costs and identifies secured or potential funding sources.
6.1.6. An open record public hearing was held by the East Wenatchee Planning Commission on May 28, 2019.
City of East Wenatchee Resolution 2019-11 – Six Year TIP Page 3 of 4
6.1.7. By this reference, the planning staff file of records, including the staff report, noticing documents and SEPA documents are entered into the record.
6.1.8. Any Conclusion of Law that is more correctly a Finding of Fact is hereby incorporated as such by this reference.
6.2. Conclusions
6.2.1. It is the determination of the responsible lead agency that no more than a moderate effect on the environment is a reasonable probability as a result of the proposed action. The proper exercise of the threshold determination process as required by WAC 197-11 is than an environmental impact statement is not required to be prepared for this project. The processing of the proposal complies with the procedural and substantive requirements of the State Environmental Policy Act, chapter 43.21C RCW and chapter 18.06 EWMC.
6.2.2. The processing of the proposal complies with the procedural and substantive requirements of RCW 35.77.010.
6.2.3. Proper legal requirements of Title 19 EWMC were met and the community was given the opportunity to comment on the proposal at a duly noticed public hearing.
6.2.4. The proposed TIP is consistent with and implements the goals and policies in the comprehensive plan.
6.2.5. The proposed TIP is consistent with and implements the policies in the Capital Facilities Plan.
6.2.6. The proposal will not be detrimental to the general public health, safety or welfare.
6.2.7. Any Finding of Fact that is more correctly a Conclusion of Law is hereby incorporated as such by this reference.
7. Filing of Program. To meet the requirements set forth in RCW 35.77.010, the Council authorizes and directs the City Clerk to file a copy of this resolution, together with Exhibit A, with the Secretary of Transportation, the Transportation Improvement Board for the State of Washington, and the Chelan Douglas Transportation Council.
8. Severability. If a court of competent jurisdiction declares any provision in this resolution to be contrary to law, such declaration shall not affect the validity of the other provisions of this Resolution.
9. Effective date. This Resolution becomes effective immediately.
City of East Wenatchee Exhibit A
Priority
Number Project Title
Project
Length
(Miles)
Project Description
Total
Estimated
Cost
Year 1
2020
Year 2
2021
Year 3
2022
Year 4
2023
Year 5
2024
Year 6
2025 Phase
Phase
Start
Year
Federal
Fund
Code
Federal
Funds
State
Fund
Code
State
Funds
Local
Funds
9th Street NE and Valley Mall Parkway Intersection 0.00 Construct new intersection traffic control 1,042,474 156,371 PE 2020 STP(R)135,261 21,110
Improvements system at 9th St. NE and Valley Mall RW
Parkway 886,103 CN 2021 STP(R)766,479 119,624CN2015
10th Street NE Reconstruction 0.95 Full reconstruction project: Center left 6,100,000 13,000 PE 2019 600,000
Eastmont Ave to Kentucky Ave turn lane, curb, gutter and sidewalk,RW 2019 150,000
stormwater conveyance and illumination 5,350,000 CN 2022 STBG 865,000 4,485,000
5th St NE Pedestrian Facilities-Phase II Curb, gutter and sidewalk or pedestrian 4,631,136 306,425 214,283 PE 2020 SRTS 442,602 78,106
Kentucky Avenue to N. Grover Pl Pathway, RRFB's and Illumination 195,000 RW 2020 SRTS 165,750 29,250
3,915,428 CN 2021 SRTS 3,328,114 587,314
Intersection Improvement 0.00 Install new roundabout 875,000 PE 2019 TIB 148,750 26,250
3rd Street SE and Highline Drive RW
700,000 CN 2020 TIB 595,000 105,000 Repair east and westbound approach 650,000 50,000 50,000 PE 2020 STPG 86,500 13,500
lanes at Grant Rd and Eastmont Ave RW
intersection 550,000 CN 2121 STPG 475,750 74,250
6 TBD - S Keller Ave (1st St SE to 3rd St SE) 0.25 Residential Overlay Program 132,080 132,080 ALL 2020 132,080
7 TBD - Clements Circle (13th St NE to 13 St NE [loop])0.24 Residential Overlay Program 176,800 176,800 ALL 2020 176,800
19th Street NW Reconstruction Phase 1 NW Cascade Ave to 0.25 Center turn lane, curb, gutter and sidewalk,
stormwater conveyance
2,694,000 PE
RW
2019 ECY 250,000
SR 28 and street illumination.2,444,000 CN 2022 TIB 2,077,400 366,600
10 TBD- N Colorado Ave (Colby Ct to 3rd St NE) 0.46 Residential Overlay Program 227,136 227,136 ALL 2021 227,136
11 TBD- Dayton Ave (6th St NE to 5th St NE) 0.15 Residential Overlay Program 59,488 59,488 ALL 2021 59,488
Eastmont Avenue / 11th St NE Traffic Signal or RAB 640,000 60,000 PE 2024 STBG 51,900 8,100
Intersection Improvements 580,000 CN 2025 STBG 501,700 78,300
13 Kentucky Avenue Reconstruction 1.03 Full reconstruction project: center left turn 6,350,400 6,350,400 ALL 2025 TIB 3,238,704 3,111,696
stormwater conveyance and street
14 TBD - 6th St NE (Colorado Ave to Eastmont Ave) 0.22 Residential Overlay Program 140,608 140,608 ALL 2022 140,608
15 TBD - Hamilton Ave (Standerfer Ave to Dead-end) 0.13 Residential Overlay Program 70,866 70,866 ALL 2022 70,866
16 TBD - Standerfer Ave (Valley Mall Parkway to Hamilton Ave) 0.04 Residential Overlay Program 30,934 30,934 ALL 2022 30,934
17 TBD - Harrison Ct (10th St NE to Jackson Ave) 0.15 Residential Overlay Program 129,359 129,359 ALL 2022 129,359
18 TBD - Parkroy Place SE/2nd St SE (S Iowa Ave to S Houston
Ave) 0.37 Residential Overlay Program 245,670 245,670 ALL 2023 245,670
19 TBD - Green Pl (Grant Rd to Dead-end) 0.11 Residential Overlay Program 145,998 145,998 ALL 2024 145,998
20 TBD - S Georgia Ave (Grant Rd to Dead-end) 0.11 Residential Overlay Program 75,432 75,432 ALL 2024 75,432
65,520
0.65
65,520 ALL 2020
9
TBD - 4th St NE (Johnson Pl to Colorado Ave)0.11 Residential Overlay Program 65,5208
From 2020 to 2025Six Year Transportation Improvement Program
Grant Road/Eastmont Ave Intersection Repair 0.00
Expenditures
1
2
3
4
5
12
S:\Public Works\STIP\TIP & STIP 2020 - 2025\Exh A 2020 TIP_FINAL 4.30.19.xlsx
City of East Wenatchee Exhibit A
Priority
Number Project Title
Project
Length
(Miles)
Project Description
Total
Estimated
Cost
Year 1
2020
Year 2
2021
Year 3
2022
Year 4
2023
Year 5
2024
Year 6
2025 Phase
Phase
Start
Year
Federal
Fund
Code
Federal
Funds
State
Fund
Code
State
Funds
Local
Funds
From 2020 to 2025Six Year Transportation Improvement Program
Expenditures
21 TBD - S Gilmore Ave (Grant Rd to Dead-end) 0.10 Residential Overlay Program 70,566 70,566 ALL 2024 70,566
19th Street NE Reconstruction- Phase II 0.24 Full reconstruction project. Center turn 1,669,680 250,452 PE 2024 TIB 212,884 37,568
stormwater conveyance and street 1,419,228 CN 2025 TIB 1,206,344 212,884
23 Eastmont Ave Preservation (9th St NE to North City Limit)1.20 Full width mill and repave.1,246,000 110,000 100,000 PE 2024 TIB 178,500 31,500
Update sidewalks to ADA standard 1,036,000 CN 2025 TIB 880,600 155,400
5th St NE Pedestrian Facilities-Phase III Curb, gutter and sidewalk or pedestrian 1,600,000 193,000 PE 2024 TIB 173,700 19,300
24 Eastmont Avenue to N. Grover Ave 0.28 pathway, Illumination, and intersection RW
improvement at Eastmont Ave 1,407,000 CN 2025 TIB 1,266,300 140,700
5th St NE Preservation (Eastmont Ave to Kentucky Ave)1.10 Full pavement reconstruction 740,000 90,000 PE 2023 TIB 76,500 13,500
650,000 CN 2024 TIB 552,500 97,500
19th Street NE Reconstruction- Phase III 0.58 Full reconstruction project, center turn 3,736,000 560,400 PE 2023 TIB 396,900 163,500
Baker Avenue to Eastmont Avenue lane, curb, gutter and sidewalk, storm- RW
water conveyance & street illumination.3,175,600 CN 2024 TIB 2,249,100 926,500
Eastmont Avenue / 19th St NE Traffic Signal or RAB 660,000 60,000 PE 2024 STBG 51,900 8,100
Intersection Improvements 600,000 CN 2025 STBG 519,000 81,000
28 Non-Motorized - Citywide Provide sidewalks, crosswalks, signal
modifications and bicycle facilities.300,000 100,000 100,000 100,000 ALL 2022 CDBG 300,000
Intersection Improvement 0.01 Install new signal with optical detection 450,000 49,000 5,000 PE 2022 STBG 46,710 7,290
3rd St SE and Rock Island Drive or RAB 396,000 CN 2023 STBG 342,540 53,460
30 Pavement preservation - Non TBD Projects Asphalt overlay, chip seal, crack sealing
and other methods 1,773,000 150,000 175,000 362,000 362,000 362,000 362,000 ALL 2022 1,773,000
31 Valley Mall Parkway Enhancement - Stage 1
From 6th Street NE to 9th Street NE 0.24 Widen sidewalks, reconfigure on street
parking.928,000 928,000 ALL 2023 STBG 802,720 125,280
32 Valley Mall Parkway Enhancement - Stage 2
From 9th Street NE to SR 28 0.39 Widen sidewalks, reconfigure on street
parking.720,000 720,000 ALL 2024 STBG 622,800 97,200
Legend TOTALS 38,376,147 1,945,196 6,077,438 8,576,767 1,198,670 3,565,848 15,850,228 5,568,260 17,439,648 15,368,239
Projects with Secured Funding Highlighted in Yellow
PE - Engineering
CN - Construction
RW - Right of Way
29
22
25
26
27
S:\Public Works\STIP\TIP & STIP 2020 - 2025\Exh A 2020 TIP_FINAL 4.30.19.xlsx
Grant RdSunset HwyEastmont AveSR 283rd St NE
5th St NEN Baker Ave11th St
N
E
10th St NE
SR 285
N James AveN Keller Ave4th St SE
8th St NE
19th St NE
15th St NE
N Grover Ave9th St N
E
Valley
Ma
l
l
Pkwy
3rd St SE N Kentucky AveHighline DrTedford St SE
12th St NE
N Iowa AveN June AveR
o
c
k
I
s
l
a
n
d
R
d
P
a
c
e
D
r
S Kentucky AveRiverview DrS Jarvis AveN Joseph AveN Kansas AveN Ashland AveSimon St N Jennifer Ln1st St SECount
ry
C
lub
D
r Bri
a
rw
o
o
d
T
e
rHolly Ln4th St NE
Dale St SEN Jackson Ave7th St N
E
S Houston Ave2nd St SE N Georgia AveS Iowa Ave2nd St
N
E Bri
a
rw
o
o
d
D
r
13th St NE
Kenroy TerN Arbor TerN A
lv
in
C
t
Bel Air Dr
19th St NW
1st Pl SEN Grover PlHannah WayEastridge DrS Keller AveBadger
M
o
u
n
t
a
i
n
R
d
N Astor CtN Aurora AveN Gale PlKing Pl
Huntwood Ln14th St NE
N Hanford AveRidgemont DrN Anne AveN Jonathon AveS James AveRolfs Pl N Jerome LnRolfs CtFairmont AveElva Way SEHarrington LnTerrace Ct NES Georgia AveEasthills Ter
17th St NE
20th St NE
N Denis CtFrench
Ave
Hill
s
i
d
e
D
r
Parkroy Pl
6th St N
E
Manzanal St NE
Mis
a
w
a
W
a
y
Etta St NECedar Ln12th Pl NE
Amy Ct
Brenne
r
LnN Gale AveHamil
ton
Ave
Copper Loop
Harrison CtN Devon AveFrance St NE
Darwood
AveN Day
ton
Ave
Degage St
18th St NE
S Jackson AveVista Vie
w
P
l
Corum
C
i
r
N Green PlN Jackson PlN Kent TerWelch Ln
Ironwood Pl
Gilbert CtGarden PlzSki View Pl
Sheri Ct
Linda CtNW Avon Ct5th St NE
8th St NE
1st St SES Iowa Ave8th St N
E
3rd St SE
2nd St SE
12th St NE
13th St NE
N Kansas Ave2nd St SE
19
t
h
S
t
N
E
N Anne Ave2nd St NE
This map is intended for general purposes only. The City of
East Wenatchee makes no representation as to the accuracy
or current condition of the data shown on this map.
6-Year Transportation Benefit District Project Schedule
.
0 0.5 10.25 MilesOverlay Year
2019
2020
2021
2022
2023
2024
Exhibit C to Staff Report
Presented at Hearing on 5/28/2019
Exhibit 2